Project progress Status

Item

Progress

Improvement of NR 56A
  • Detailed design works was completed on 20 April 2011
  • Bidding was completed on 2 November 2011
  • Contract Agreement with Contractor was signed on 25 November 2011
  • Notice to Commence issued on 12 March 2012 at no resettlement impact section
  • Clearing and grubbing work is ongoing
Improvement of Cross Border Facilities at O’smach
  • Detailed design works was completed on 8 November 2011
  • Invitation for Bid was announced on 3 January 2012.
  • Bid submission and bid opening was held on 16 February 2012
  • Bid evaluation is ongoing
Road Maintenance Program
  • Draft Bidding documents for civil work and equipment are completed
Road Safety Program
  • EOI for recruitment of consultant was announced on 20 April 2012
HIV Prevention and Anti-Human-Trafficking Program
  • Contract Agreement with Consultant was signed on 22 February 2011
  • Notice to Commence issued on 23 February 2012 and program is in progress

Overall Project Physical Progress

Component

Contract

Contract Amount

(US$)

Physical Progress

Remarks

1. Civil Works

CW1 (NR56A)

6,735,689.49

4.0 %

CW3 (CBF)

NA

-

Not yet selected

CW4 (RSP)

NA

-

Not yet selected

2. Consulting Services

CS1 (DDIS)

1,694,862

41.0 %

CS3 (Road Safety Program)

NA

-

Not yet selected

CS4 (HIV)

247,724

0.5 %

3.Equipment

EQ2 (Road Maintenance Program)

NA

-

Not yet selected

Civil Works for Weigh Stations

NA

-

Not yet selected

Overall Progress (%)

24.6 %